News
 
Alley Way Repair Project, which will occur in phases, is to ensure continued trash pickup from alleyways by Waste Connections/Town of Huntersville.  
Additional information on Alley Way Repair Project is available to Monteith Park owners on Pilera
 
Phase 1 Alley Way Repair starts on October 21
Please NOTE:
  • Alley will be closed and not accessible by auto for the duration of construction (estimated at 5 days, weather permitting).
  • Alternate parking must be found. Do NOT block mailboxes of community members which will prohibit mail delivery.
  • Trash collection will also not occur for your alley during this period.
  • Mark/protect landscape and other items (e.g. sprinkler heads) close to the edges of alley ways.
  • All movable items such as nets or goals should be moved prior from construction zones 
 
Phase 1: Alley Update [Feather Oaks] (week of 1/20/20) 
The paving schedule for the week of 1/20 is as follows:
  • Start work on Feather Oak.
Note:  We will only be working on the section of Feather Oak that runs parallel to Stumptown Road.  This will impact homes facing Stumptown Road; addresses 13516 thru 13532 (five homes).  
Stumptown homeowners can put their trashcans for pickup during construction at the yellow marked area (see image).
 
Phase 1: Alley Update [Aiken and Feather Oaks] (1/6/20) 
The paving schedule for the week of 1/6 is as follows:
  • Wednesday 1/8 - plan on paving the remainder of Aiken if it has dried out enough from rain on 1/7.
  • Thursday 1/9 - Finish Aiken if not already done.  Start demo work on Feather Oak.
  • Friday 1/10 - Continue work on Feather Oak.
Note:  We will only be working on the section of Feather Oak that runs parallel to Stumptown Road.  This will impact homes facing Stumptown Road; addresses 13516 thru 13532 (five homes).  
Stumptown homeowners can put their trashcans for pickup during construction at the yellow marked area (see image).
 
Phase 1: Alley Update [Aiken and Feather Oaks] (12/31/19) 
JLS is replacing the sidewalks today on Aiken, clean up and seed any disturbed areas.  The remaining section of Aiken will be demolished tomorrow, hopefully they to get the section complete this week (12/30) and then move over to Feather Oaks next week (1/6).
 
 
Phase 1: Aiken Alley Update (11/13/19) > TRASH PICK UP
Those living on Aiken Alley will have trash pickup tomorrow, Thursday November 14th. Please leave your trash cans out on the driveway. They will be rolled out and placed back after pickup. The paving project has been delayed due to the weather conditions. It will resume once the ground has thawed and the areas have dried out. Thank you for your patience.
 
 
Phase 1: Aiken Alley Update (11/11/19)
Week of 11/11: 
a. Construction continues and based on current progress and depending on weather delays asphalt paving will occur on Tuesday, Nov. 12th.  
b. Storm drain installation and some concrete repair work will occur after the asphalt is down but every effort will be made to get homeowners access to their garages as soon as possible after paving.  
We will publish a bulletin as soon as we get the green light from Woodbine on opening access to completed Aiken sections.
 
On/near 11/13: Plan to Start construction on section of Aiken between Shinner Drive and Copley Square Drive.
 
Trash pickup:
- If approved for traffic by Thursday 11/14 trash pickup will resume as normal for the paved part of Aiken. 
- For areas of Aiken just starting: Homeowners should plan on taking their containers to the curb on Copley Square and put them with the other containers that get emptied there.  
We will publish any additional information on trash pickup per construction status.
 
 
Phase 1: Aiken Alley Update (11/3/19)
Planned activities based on current weather forecast of no rain until Friday, 11/8.
1. Completing the current section of Aiken (if the area is dry before Monday, 11/4). 
2. Homeowners may have to coordinate trash pickup again for the week of 11/4. Announcements will be made on Tuesday based on work progress.
3. Next section of Aiken will likely start the week of 11/11. 
Issues with Cable/Internet should be directed to the utility provider.
 
 
Phase 1: Aiken Alley Update (10/30/19) > TRASH PICK UP
Residents should place trash cans out WEDNESDAY for Thursday pick-up.
The construction contractor will take the cans to Shinner Drive for Waste Connections pick up and return to your location once done.
For additional information contact Beth Wilkins, beth@csiproperties.com
 
Phase 1: Aiken Alley Update (10/25/19)
Key items have delayed the scheduled work on Aiken started 10/21:
1) Weather: Heavy rain at the first of the week stopped work and then water saturating the soil delayed work afterwards.  Going forward, rain will be the biggest cause of delays.
2) Soil Conditions: Wet conditions modify the type and speed of work required so that the base under the new asphalt is as required for proper, long term stability
 
As with any construction project, the following can impact schedules:
  • Weather forecasts are reviewed to determine if/what work can begin to avoid having to complete tasks twice.  
  • Certain work tasks require time for installed materials to settle before the next step can begin.
  • Tasks that required gravel, concrete or asphalt are limited to weekdays as supply companies are not open on Saturday.
Homeowners with sprinklers running near the alleys undergoing construction are asked to please TURN THEM OFF WHILE WORK IS BEING DONE to avoid any additional impact to installed materials.
 
Projected Timeline:
10/28-29: Continued undercutting on Aiken
10/31: Paving on Aiken to commence
Week of 11/4: Work on section of Aiken between Shinner Drive and Copley Square Drive